Term 1 Week 3
Retro
Reflect on the previous time period
| Notes | Actionables |
---|---|---|
What was completed? | Completed most of the starter tasks assigned to the members |
|
What was done well? | We had all the tasks in Jira and labelled accordingly and got most of the starter tasks completed |
|
What could have been done better? | For one of the tasks we figured it was actually better before so it won’t be used in the end |
|
Planning
Update plans for the future
| Notes | Actionables |
---|---|---|
Short term goals (achieve by next retro) | Complete some of the subtasks for some of the bigger projects (still to be figured out) |
|
Medium term goals (review at next retro) | The projects and how they’re going (avl visualiser, code snippets, etc) |
|
Timeline (ETA until release, etc) | AVL visualiser (1 month) Code snippets (1- 2 months) Visualiser general improvements (1 month) |
|
Misc
Random stuff
|
|
---|---|
|
|
|
|
Related content